Baturaden Geothermal Power Plant is a 220MW geothermal power project. It is planned in Central Java, Indonesia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in 2024. Buy the profile here.
Description
The project is being developed by PT Sejahtera Alam Energy. PT Nirwana Suci Abadi and PT Trinergy Mandiri International are currently owning the project having ownership stake of 89% and 11% respectively.
The project is expected to supply enough clean energy to power 220,000 households.
Development status
Post completion of the construction, the project is expected to get commissioned in 2024.
Power purchase agreement
The power generated from the project will be sold to PT PLN (Persero) under a power purchase agreement at the rate of $0.095kWh.
For more details on Baturaden Geothermal Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.