Ayamonte Wind Farm is a 34.8MW onshore wind power project. It is located in Andalusia, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2022 and subsequently entered into commercial operation in December 2023. Buy the profile here.
Description
The project was developed by Capital Energy Power Vortice SLU. Verbund and Capital Energy Power Vortice SLU are currently owning the project having ownership stake of 70% and 30% respectively.
The project generates 78,400MWh electricity and supplies enough clean energy to power 29,000 households, offsetting 58,000t of carbon dioxide emissions (CO2) a year.
Development status
The project is currently active. The project construction commenced in 2022 and subsequently entered into commercial operation in December 2023.
Contractors involved
GE Renewable Energy was selected as the turbine supplier for the wind power project. The wind power project consists of 6 turbines.
GE Renewable Energy is the O&M contractor for the wind power project. The operation and maintenance contract commenced from 2023, for a period of 20 years.
The wind power project consists of 120.9m high towers supplied by LM Wind Power Holding.
The rotor blades have been supplied by LM Wind Power Holding. The blade length is 158.000m.
For more details on Ayamonte Wind Farm, buy the profile here.
About Capital Energy Power Vortice SLU
Capital Energy Power Vortice SLU (Capital Energy Power) develops, generates and supplies renewable energy. Capital Energy Power is headquartered in Spain.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.