Bismayah Combined Cycle Power Plant IWPP is a 4,580MW dual-fuel fired power project. It is located in Baghdad, Iraq. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 2017. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Bismayah Combined Cycle Power Plant IWPP

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is developed and owned by Mass Group Holding.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel.

Development status

The project got commissioned in 2017.

Power purchase agreement

The power generated from the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase III) is sold to Ministry of Electricity, Iraq under a power purchase agreement for a period of 20 years.

Contractors involved

Avax was selected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block III) project. Avax was selected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block IV) project. ENKA Insaat ve Sanayi was selected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Gas Turbine I)) project. ENKA Insaat ve Sanayi was selected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Steam Turbine)) project. ENKA Insaat ve Sanayi was selected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I(Gas Turbine II)) project. ENKA Insaat ve Sanayi was selected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine I)) project. ENKA Insaat ve Sanayi was selected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine II)) project. ENKA Insaat ve Sanayi was selected to render engineering procurement construction services for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Steam Turbine)) project.

Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Gas Turbine I)) is equipped with GE Power 9F.03 gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.

Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Steam Turbine)) is equipped with GE Power D200 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.

Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I(Gas Turbine II)) is equipped with GE Power 9F.03 gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.

Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine I)) is equipped with GE Power 9F.03 gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.

Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine II)) is equipped with GE Power 9F.03 gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.

Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Steam Turbine)) is equipped with GE Power D200 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.

Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block III) is equipped with GE Power 2x1 MS 9F.03 gas turbines. The phase consists of 2 gas turbines with 260MW nameplate capacity.

Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block III) is equipped with GE Power 2x1 MS D200 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.

Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block IV) is equipped with GE Power 2x1 MS 9F.03 gas turbines. The phase consists of 2 gas turbines with 260MW nameplate capacity.

Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase II Block IV) is equipped with GE Power 2x1 MS D200 steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.

Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase III) is equipped with GE Power 9F.04 gas turbines. The phase consists of 4 gas turbines.

GE Power supplied electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Gas Turbine I)).

GE Power supplied electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I (Steam Turbine)).

GE Power supplied electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block I(Gas Turbine II)).

GE Power supplied electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine I)).

GE Power supplied electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Gas Turbine II)).

GE Power supplied electric generator for the Bismayah Combined Cycle Power Plant IWPP (Bismayah Combined Cycle Power Plant IWPP Phase I Block II (Steam Turbine)).

John Cockerill Group supplied steam boiler for the project.

GE Power is the O&M contractor for thermal power project for a period of 20 years.

For more details on Bismayah Combined Cycle Power Plant IWPP, buy the profile here.

About Mass Group Holding

Mass Group Holding Ltd (Mass Group) is a diversified company. The company's business segments include power generation of electricity, cement production, steel and iron production. The company’s power generation segment offers power stations, gas power stations and wind power stations operations, management and development services. Its cement production segment offers ordinary, sulfate-resistant cement and others. Mass Group’s steel and iron production segment manufactures industrial steel products, treatment furnaces and others. The company has operations in Jordan and Iraq. Mass Group is headquartered in Amman, Jordan.