Dubrovnik is a 252MW hydro power project. It is located on Trebisnjice river/basin in Dubrovnik-Neretva, Croatia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1965. Buy the profile here.
Description
The project is currently owned by HEP-Proizvodnja.
Dubrovnik is a reservoir based project. The net head of the project is 272m. Dubrovnik underwent through rehabilitation & modernization during 2013- 2015. The project generated 766.2 GWh of electricity.
The project has 2 electric generators installed at the site. The generator capacity is 140 MVA.
Development status
The project got commissioned in 1965.
Power purchase agreement
The power generated from the project is sold to Elektroprivreda Republike Srpske under a power purchase agreement.
Contractors involved
Litostroj Power was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines, each with 126MW nameplate capacity.
For more details on Dubrovnik, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.