Governador Leonel Brizola (TermoRio) Combined Cycle Power Plant is a 1,058MW gas fired power project. It is located in Rio de Janeiro, Brazil. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in November 2004. Buy the profile here.
Description
The project is currently owned by Petroleo Brasileiro with a stake of 100%.
It is a CCGT with Cogen power plant.
Development status
The project got commissioned in November 2004.
Contractors involved
GE Power was selected to render engineering procurement construction services for the gas fired power project.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 3 units of DKZ1/DKZ2 steam turbines.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 6 units of GT11N2 gas turbines.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
John Cockerill Group supplied steam boiler for the project.
John Cockerill Group supplied steam boiler for the project.
John Cockerill Group supplied steam boiler for the project.
John Cockerill Group supplied steam boiler for the project.
GE Power is the O&M contractor for thermal power project. The operation and maintenance contract commenced from 2013, for a period of 7 years.
For more details on Governador Leonel Brizola (TermoRio) Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.