Valladolid III Combined Cycle Power Plant is a 525MW gas fired power project. It is located in Yucatan, Mexico. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in June 2006. Buy the profile here.
Description
The project is co-owned by JERA and Mitsui, with their respective ownership stake of 50% each.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
The project generated 2,736,000MWh of electricity.
Development status
The project got commissioned in June 2006.
Power purchase agreement
The power generated from the project is sold to Comision Federal de Electricidad under a power purchase agreement for a period of 25 years.
Contractors involved
Mitsui and Toshiba JSW Power Systems were selected to render engineering procurement construction services for the gas fired power project.
The Gas fired project have been supplied by GE Power and Toshiba Energy Systems and Solutions.
The electric generators for the project were procured from GE Power and Toshiba Energy Systems and Solutions.
Cerrey supplied steam boiler for the project.
Cerrey supplied steam boiler for the project.
Cerrey supplied steam boiler for the project.
For more details on Valladolid III Combined Cycle Power Plant, buy the profile here.