Surgutskaya GRES-2 Combined Cycle Power Plant is an 807.1MW gas fired power project. It is located in Tyumen, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in July 2011. Buy the profile here.
Description
The project is currently owned by Unipro with a stake of 100%.
It is a CCGT with Cogen power plant. The fuel is procured from PAO NOVATEK.
Development status
The project got commissioned in July 2011.
Contractors involved
Gama Power Systems Engineering and Contracting and General Electric International were selected to render engineering procurement construction services for the gas fired power project.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of 9FA gas turbines.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of D10 steam turbine;gas turbines.
GE Power supplied 390H electric generator for the project.
GE Power supplied 390H electric generator for the project.
John Cockerill Group supplied steam boiler for the project.
John Cockerill Group supplied steam boiler for the project.
GE Power is the O&M contractor for thermal power project. The operation and maintenance contract commenced from 2011, for a period of 12 years.
For more details on Surgutskaya GRES-2 Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.