Kurshav is a 221MW hydro power project. It is located on Kuban, Stavropol canal river/basin in Karachay–Cherkessia, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. The project construction commenced in 1962 and subsequently entered into commercial operation in 1967. Buy the profile here.
Description
The project is currently owned by RusHydro with a stake of 100%.
The project generated 728.05 GWh of electricity.
Development status
The project construction commenced in 1962 and subsequently entered into commercial operation in 1967.
Contractors involved
Kurshav (Kurshav-1) is equipped with Kharkovsky HTGZ turbines. The phase consists of 2 turbines, each with 18.5MW nameplate capacity.
Kurshav (Kurshav-2) is equipped with Kharkovsky HTGZ turbines. The phase consists of 4 turbines, each with 46MW nameplate capacity.
Uralelectrotyazhmash was selected as the generator supplier for the hydro power project. The project consists of 6 generators.
For more details on Kurshav, buy the profile here.