Aoos is a 210MW hydro power project. It is located on Aoos river/basin in Epirus, Greece. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1990. Buy the profile here.
Description
The project is currently owned by Public Power.
The hydro reservoir capacity is 144.5 million cubic meter. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 2 in number. The penstock length is 1,100m. The penstock diameter is 3.5m. The project generated 165 GWh of electricity.
Development status
The project got commissioned in 1990.
Contractors involved
Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 2 units of pelton turbines, each with 105MW nameplate capacity.
GE Renewable Energy supplied electric generator(s) for the project.
For more details on Aoos, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.