Aimores is a 330MW hydro power project. It is located on Doce river/basin in Minas Gerais, Brazil. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2001 and subsequently entered into commercial operation in 2006. Buy the profile here.
Description
The project is currently owned by Alianca Geracao de Energia with a stake of 100%.
Aimores is a run-of-river project. The hydro reservoir capacity is 184.6 million cubic meter. The gross head and net head of the project are 26.9m and 25.8m respectively.
Development status
The project construction commenced in 2001 and subsequently entered into commercial operation in 2006.
Contractors involved
Voith Hydro Holding was selected as the turbine supplier for the hydro power project. The company provided 3 units of kaplan turbines, each with 110MW nameplate capacity.
Voith Hydro Holding supplied 3 electric generators for the project. The generator capacity is 116 MVA.
For more details on Aimores, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.