W S Lee Combined Cycle Power Plant is an 846.7MW gas fired power project. It is located in South Carolina, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in April 2018. Buy the profile here.
Description
Duke Energy Carolinas and North Carolina Electric Membership are currently owning the project having ownership stake of 87.27% and 12.73% respectively.
It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Middle load. The fuel is procured from Piedmont Natural Gas.
The project generated 3,523,669MWh of electricity.
Development status
The project got commissioned in April 2018.
Contractors involved
Fluor was selected to render engineering procurement construction services for the gas fired power project.
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 2 gas turbines, each with 242.3MW nameplate capacity.
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 1 steam turbine with 362.1MW nameplate capacity.
Siemens supplied electric generator for the project.
Siemens supplied electric generator for the project.
Vogt Power International supplied steam boiler for the project.
Vogt Power International supplied steam boiler for the project.
For more details on W S Lee Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.