Sostanj Steam Turbine Power Plant is a 755MW coal fired power project. It is located in Savinja, Slovenia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in May 1956. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Sostanj Steam Turbine Power Plant

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by Termoelektrarna Sostanj with a stake of 100%.

It is a Steam Turbine with Cogen power plant. The fuel is procured from Premogovnik Velenje Coal Mine.

Development status

The project got commissioned in May 1956.

Contractors involved

Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit I) is equipped with Andritz Hydro steam turbine. The phase consists of 1 steam turbine with 30MW nameplate capacity.

Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit II) is equipped with Andritz Hydro steam turbine. The phase consists of 1 steam turbine with 30MW nameplate capacity.

Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit III) is equipped with Andritz Hydro steam turbine. The phase consists of 1 steam turbine with 75MW nameplate capacity.

Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit IV) is equipped with Siemens Multistage, Extraction, Condensing steam turbine. The phase consists of 1 steam turbine with 275MW nameplate capacity.

Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit V) is equipped with Siemens Multistage, Extraction, Condensing steam turbine. The phase consists of 1 steam turbine with 345MW nameplate capacity.

ABB supplied Synchronous, Air Cooled electric generator for the Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit I).

ABB supplied Synchronous, Air Cooled electric generator for the Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit II).

ABB supplied Synchronous, Hydrogen Cooled electric generator for the Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit III).

Siemens supplied Synchronous, Hydrogen Cooled electric generator for the Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit IV).

Siemens supplied Synchronous, Hydrogen Cooled electric generator for the Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit V).

Sulzer supplied steam boiler for the Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit I).

Sulzer supplied steam boiler for the Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit II).

Sulzer supplied steam boiler for the Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit III).

Babcock & Wilcox Enterprises supplied steam boiler for the Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit IV).

Sulzer supplied steam boiler for the Sostanj Steam Turbine Power Plant (Sostanj Steam Turbine Power Plant Unit V).

For more details on Sostanj Steam Turbine Power Plant, buy the profile here.

This content was updated on 14 October 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.