Goseong Green Power Plant is a 2,080MW coal fired power project. It is located in South Gyeongsang, South Korea. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. The project construction commenced in 2017 and subsequently entered into commercial operation in May 2021. Buy the profile here.
Description
The project was developed by Goseong Green Power. KDB Infrastructure Investment Asset Management, Korea Midland Power, SK Gas and SK Ecoplant are currently owning the project having ownership stake of 42%, 29%, 19% and 10% respectively.
It is a Steam Turbine power plant.
Development status
The project construction commenced in 2017 and subsequently entered into commercial operation in May 2021.
Contractors involved
Seohee Construction and SK Ecoplant were selected to render engineering procurement construction services for the coal fired power project.
Doosan Enerbility was selected as the turbine supplier for the Coal fired project. The company provided 2 units of TC4F steam turbines, each with 1,040MW nameplate capacity.
Doosan Enerbility supplied steam boiler for the project.
Doosan Enerbility supplied steam boiler for the project.
Doosan Enerbility supplied steam boiler for the project.
Doosan Enerbility supplied steam boiler for the project.
Korea Electric Power Industrial Development and Korea South-East Power were contracted to render operations & maintenance services for the project.
For more details on Goseong Green Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.