ACWA Kirikkale Combined Cycle Power Plant is a 947.2MW gas fired power project. It is located in Kirikkale, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in November 2017. Buy the profile here.
Description
The project was developed by Acwa Guc Elektrik Isletme ve Yonetim Sanayi ve Tic. The project is currently owned by Acwa Power with a stake of 69.6% and Samsung C&T.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
Development status
The project got commissioned in November 2017.
Contractors involved
Samsung C&T was selected to render engineering procurement construction services for the gas fired power project.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 steam turbine with 328MW nameplate capacity.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of GT26 gas turbines, each with 309.6MW nameplate capacity.
GE Power supplied electric generator for the project.
GE Power supplied electric generator for the project.
GE Power supplied steam boiler for the project.
GE Power supplied steam boiler for the project.
Nomac Enerji Uretim Isletme Ve Bakim Hizmetleri Ltd Sirketi is the O&M contractor for thermal power project.
For more details on ACWA Kirikkale Combined Cycle Power Plant, buy the profile here.