The Cirebon Power Plant is 1,660MW coal fired power project. It is planned in West Java, Indonesia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the partially active stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in July 2012. Buy the profile here.
Description
The project is being developed by JERA Power (Thailand) and Pt Cirebon Electric Power. Marubeni, PT Indika Energy, ST International, JERA and Korea Midland Power are currently owning the project having ownership stake of 35%, 25%, 20%, 10% and 10% respectively.
It is a Steam Turbine power plant.
Development status
Post completion of the construction, the project is expected to get commissioned in July 2012.
Power purchase agreement
The power generated from the Cirebon Power Plant (Cirebon Power Plant Phase I) will be sold to PT PLN (Persero) under a power purchase agreement for a period of 30 years.
The power generated from the Cirebon Power Plant (Cirebon Power Plant Phase II) will be sold to PT PLN (Persero) under a power purchase agreement for a period of 25 years.
Contractors involved
Doosan Enerbility is expected to render engineering procurement construction services for the Cirebon Power Plant (Cirebon Power Plant Phase I) project. Hyundai Engineering & Construction is expected to render engineering procurement construction services for the Cirebon Power Plant (Cirebon Power Plant Phase II) project. Mitsubishi Power is expected to render engineering procurement construction services for the Cirebon Power Plant (Cirebon Power Plant Phase II) project. Toshiba Energy Systems and Solutions is expected to render engineering procurement construction services for the Cirebon Power Plant (Cirebon Power Plant Phase II) project.
The Coal fired project will be supplied by Doosan Enerbility and Toshiba Energy Systems and Solutions.
Doosan Enerbility is expected to be the supplier of electric generator for the Cirebon Power Plant (Cirebon Power Plant Phase I).
Doosan Enerbility is expected to be the supplier of electric generator for the Cirebon Power Plant (Cirebon Power Plant Phase I).
Doosan Enerbility is expected to be the supplier of electric generator for the Cirebon Power Plant (Cirebon Power Plant Phase I).
Doosan Enerbility is expected to be the supplier of electric generator for the Cirebon Power Plant (Cirebon Power Plant Phase I).
Doosan Enerbility is expected to be the supplier of electric generator for the Cirebon Power Plant (Cirebon Power Plant Phase I).
Doosan Enerbility is likely to be the supplier of steam boiler for the Cirebon Power Plant (Cirebon Power Plant Phase I).
Doosan Enerbility is likely to be the supplier of steam boiler for the Cirebon Power Plant (Cirebon Power Plant Phase I).
Doosan Enerbility is likely to be the supplier of steam boiler for the Cirebon Power Plant (Cirebon Power Plant Phase I).
Doosan Enerbility is likely to be the supplier of steam boiler for the Cirebon Power Plant (Cirebon Power Plant Phase I).
Doosan Enerbility is likely to be the supplier of steam boiler for the Cirebon Power Plant (Cirebon Power Plant Phase I).
Mitsubishi Power is likely to be the supplier of steam boiler for the Cirebon Power Plant (Cirebon Power Plant Phase II).
Mitsubishi Power is likely to be the supplier of steam boiler for the Cirebon Power Plant (Cirebon Power Plant Phase II).
Mitsubishi Power is likely to be the supplier of steam boiler for the Cirebon Power Plant (Cirebon Power Plant Phase II).
Mitsubishi Power is likely to be the supplier of steam boiler for the Cirebon Power Plant (Cirebon Power Plant Phase II).
Mitsubishi Power is likely to be the supplier of steam boiler for the Cirebon Power Plant (Cirebon Power Plant Phase II).
For more details on Cirebon Power Plant, buy the profile here.
About Pt Cirebon Electric Power
Pt Cirebon Electric Power is a consortium led by Japan's Marubeni Corporation. It is engaged in the development of the coal fired power plant located in Cirebon, West Java, Indonesia. The total installed capacity of the project is 660 MW.