The Muara Tawar Combined Cycle Power Plant (II,III,IV) is 1,770MW gas fired power project. It is planned in West Java, Indonesia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the partially active stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in 1997. Buy the profile here.

Smarter leaders trust GlobalData

Description

The project is being developed and currently owned by PT PLN Nusantara Power. The company has a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel will be procured from PT Nusantara Regas, Perusahaan Gas Negara (PGN), PT Pertamina EP, JOB Pertamina-Talisman Jambi Merang.

Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block II)) consists of 1 steam turbine.

Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block III)) consists of 1 steam turbine.

Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block IV)) consists of 1 steam turbine.

Development status

Post completion of the construction, the project is expected to get commissioned in 1997.

Contractors involved

Balfour Beatty is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block II)) project. Balfour Beatty is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block III)) project. Balfour Beatty is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block IV)) project. Doosan Enerbility is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block II)) project. Doosan Enerbility is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block III)) project. Doosan Enerbility is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block IV)) project. Doosan Enerbility is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block II)) project. Doosan Enerbility is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block III)) project. Doosan Enerbility is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block IV)) project. PT Hutama Karya (Persero) is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block II)) project. PT Hutama Karya (Persero) is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block III)) project. PT Hutama Karya (Persero) is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block IV)) project. PT PLN (Persero) is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block II)) project. PT PLN (Persero) is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block III)) project. PT PLN (Persero) is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Steam Turbine -Block IV)) project. Samsung C&T is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block II)) project. Samsung C&T is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block III)) project. Samsung C&T is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block IV)) project. Siemens Energy is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block II)) project. Siemens Energy is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block III)) project. Siemens Energy is expected to render engineering procurement construction services for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block IV)) project.

Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block II)) will be equipped with GE Power GT13E2 gas turbines. The phase consists of 2 gas turbines with 140MW nameplate capacity.

Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block III)) will be equipped with Siemens Energy SGT5-2000E gas turbines. The phase consists of 3 gas turbines with 140MW nameplate capacity.

Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block IV)) will be equipped with Siemens Energy SGT5-2000E gas turbines. The phase consists of 3 gas turbines with 140MW nameplate capacity.

GE Power is expected to be the supplier of electric generator for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block II)).

Siemens Energy is expected to be the supplier of electric generator for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block III)).

Siemens Energy is expected to be the supplier of electric generator for the Muara Tawar Combined Cycle Power Plant (II,III,IV) (Muara Tawar Combined Cycle Power Plant (Gas Turbine -Block IV)).

For more details on Muara Tawar Combined Cycle Power Plant (II,III,IV), buy the profile here.

About PT PLN Nusantara Power

PT PLN Nusantara Power (PLN NP), a subsidiary of PT PLN (Persero), generates and supplies electricity. It is responsible to meet the electricity requirements of the Java-Madura-Bali (JAMALI) electric system. It generates electricity from energy sources such as oil, natural gas, hydro, coal, and solar. It also offers services such as engineering, procurement, construction, installation, operations and maintenance (O&M) of power plants. The company provides education and training in power plant management and renewable energy. Its customers include PT P3B Jawa-Bali for the electricity supply business and PT PLN (Persero) for the O&M service provider and other services business. PLN NP is headquartered in Surabaya, Jawa Timur, Indonesia.

This content was updated on 11 November 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.