The Magnolia Power Generating Station is 700MW gas fired power project. It is planned in Louisiana, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. The project construction is likely to commence in 2023 and is expected to enter into commercial operation in May 2025. Buy the profile here.
Description
The project is being developed and currently owned by Kindle Energy. The company has a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant can run on dual-fuel. The primary fuel being used to power the plant will be natural gas. In case of shortage of natural gas the plant will run on Hydrogen.
Development status
The project construction is expected to commence from 2023. Subsequent to that it will enter into commercial operation by May 2025.
Power purchase agreement
The power generated from the project will be sold to 1803 Electric Cooperative under a power purchase agreement.
Contractors involved
GE Vernova will be the turbine supplier for the Gas fired project. The company is expected to provide 1 unit of 7HA.03 gas turbine.
GE Vernova will be the turbine supplier for the Gas fired project. The company is expected to provide 1 unit of STF-A650 steam turbine.
GE Vernova is likely to be the supplier of steam boiler for the project.
For more details on Magnolia Power Generating Station, buy the profile here.
About Kindle Energy
Kindle Energy LLC is a power management company. The company focuses on developing, managing, and operating assets in both international and domestic energy markets.