The Songon Combined Cycle Power Plant is 372MW gas fired power project. It is planned in Lagunes, Ivory Coast. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in multiple phases. The project construction is likely to commence in 2025 and is expected to enter into commercial operation in 2026. Buy the profile here.
Description
The project is being developed and currently owned by Songon Energies. The company has a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant can run on dual-fuel. The primary fuel being used to power the plant will be liquefied natural gas. In case of shortage of liquefied natural gas the plant will run on Heavy Fuel Oil, Diesel Oil.
The thermal power project consists of 2 turbines each with 126 MW nameplate capacity and 1 turbines each with 120 MW nameplate capacity respectively.
Development status
The project construction is expected to commence from 2025. Subsequent to that it will enter into commercial operation by 2026.
Contractors involved
China Energy Engineering Group Guangdong Power Engineering is expected to render engineering procurement construction services for the gas fired power project.
For more details on Songon Combined Cycle Power Plant, buy the profile here.
About Songon Energies
Songon Energies specializes in the generation, transmission and distribution of electricity through the combustion of coal, oil, or natural gas. The company is headquartered in Ivory Coast.
Data Insights