Siemens SylWin1

German manufacturer Siemens has completed the installation of SylWin1 grid connection in the North Sea and handed it over to network operator TenneT.

The now-operational link is located at nearly 70km from the west of Sylt island in Germany. It will allow transmission of up to 864MW of renewable energy.

The link connects three offshore wind facilities, Butendiek, DanTysk and Sandbank, which have been equipped with 232 Siemens wind turbines in total and have a generation capacity of 288MW each.

More than 100 turbines have already been connected to the grid with work for the others in progress.

"The link connects three offshore wind facilities, Butendiek, DanTysk and Sandbank, which have been equipped with 232 Siemens wind turbines in total."

The offshore platform transmits renewable energy via a 200km subsea and underground cable link to the land-based station Büttel in Germany.

The transmission capacity of SylWin1 can meet the energy requirements of more than one million households.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Siemens has implemented high-voltage direct-current (HVDC) technology for the connection, which is claimed to be ‘world’s most powerful grid connection to date’.

TenneT managing board member Lex Hartman said: "2015 is a special milestone year for TenneT, as we will be completing further offshore grid connections by the end of the year, meaning that all in all we will have implemented a capacity of more than 5,000MW, or more than two-thirds of the offshore expansion goal set by the Federal German Government by then."

Siemens has won five North Sea grid connection projects by TenneT, three of which have been turned operational this year. These are BorWin2 (800MW), HelWin1 (576MW) and SylWin1 (864MW).

The other two projects to be set up by the German firm are HelWin2 (690 MW) and BorWin3 (900 MW).


Image: The 864MW SylWin1 grid connection will transmit electricity from three offshore wind facilities. Photo: courtesy of Siemens