Jhimpir_Western Energy is a 50MW onshore wind power project. It is planned in Sindh, Pakistan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. The project construction is likely to commence in 2025 and is expected to enter into commercial operation in 2026. Buy the profile here.
Description
The project is being developed by TAPAL Energy and Western Energy. The project is currently owned by Western Energy with a stake of 100%.
The project is expected to generate 162,060MWh of electricity.
The project will have 94m high towers.
Development status
The project construction is expected to commence from 2025. Subsequent to that it will enter into commercial operation by 2026.
Power purchase agreement
The power generated from the project will be sold to Central Power Purchasing Agency under a power purchase agreement.
Contractors involved
Shanghai Marine Diesel Engine Research Institute and Sino-Qiyao International are expected to render engineering procurement construction services for the wind power project.
GE Renewable Energy will be the turbine supplier for the wind power project. The company is expected to provide 20 units of GE 2.5 - 132 turbines.
Sino-Qiyao International is expected to perform operations and maintenance for the wind power project for a period of 10 years.
For more details on Jhimpir_Western Energy, buy the profile here.
About TAPAL Energy
TAPAL Energy Private Limited (TAPAL Energy) is an energy company based in Karachi, Pakistan. The company is engaged in power generating activities. It is a joint venture independent power project of local and international investors. The company owns and operates its 126 MW thermal power plant to supply electricity to Karachi Electric Supply Company (KESC). Further, TAPAL Energy's plant has been designed, engineered and constructed by Power Construction Company BV of Holland. The plant is installed with equipments supplied from Wartsila diesel and ABB Industry of Finland, which is designed for continuous operation on Heavy fuel oil with start and stops on Light fuel oil. In addition, the company has entered into fuel supply agreement with Pakistan State Oil Company Ltd. for continuous supply of fuel.
Furthermore, the plant operational method is fully automatic for synchronizing and load sharing utilizing PLC based control system, generating power at 11 kV and further, stepped up to 132kV through three main transformers and supplied to the KESC grid system. The company is headquartered at Karachi, Pakistan.