La Bobia – San Isidro is a 49.3MW onshore wind power project. It is located in Asturias, Spain. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in May 2002. Buy the profile here.
Description
The project was developed by Terranova Energy. The project is co-owned by Acciona Energia and Eurus Energy Holdings, with their respective ownership stake of 50% each.
The project generates 125,000MWh electricity and supplies enough clean energy to power 37,500 households.
Development status
The project is currently active. The project got commissioned in May 2002.
Contractors involved
Siemens Gamesa Renewable Energy was selected as the turbine supplier for the wind power project. The company provided 58 units of G52-850 kW turbines, each with 0.85MW nameplate capacity.
Global Energy Services Siemsa is the O&M contractor for the wind power project, commencing from the year 2002.
For more details on La Bobia - San Isidro, buy the profile here.
About Terranova Energy
Terranova Energy Corp., S.A. is a Spain-based company engaged in the promotion of renewable energy. The company is especially focused in the development of wind projects. The company design, development, construction, operation and maintenance of wind mills.