Mejillones Combined Cycle Power Plant is a 250MW gas fired power project. It is located in Antofagasta, Chile. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in June 2000. Buy the profile here.
Description
Engie and Others are currently owning the project having ownership stake of 59.99% and 40.01% respectively.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel.
Development status
The project got commissioned in June 2000.
Power purchase agreement
The power generated from the project is sold to Sistema Interconectado del Norte Grande under a power purchase agreement.
Contractors involved
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 1 steam turbine with 94MW nameplate capacity.
Siemens was selected as the turbine supplier for the Gas fired project. The company provided 1 gas turbine with 156MW nameplate capacity.
Siemens supplied SGen5-100A-2P 115-36 electric generator for the project.
Siemens supplied SGen5-100A-2P 115-36 electric generator for the project.
For more details on Mejillones Combined Cycle Power Plant, buy the profile here.