Nossener Brucke Cogeneration Plant is a 270MW gas fired power project. It is located in Saxony, Germany. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1995. Buy the profile here.
Description
The project is currently owned by DREWAG - Stadtwerke Dresden with a stake of 100%.
It is a CCGT with Cogen power plant that is used for Peakload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Fuel Oil.
Development status
The project got commissioned in 1995.
Contractors involved
Siemens Energy was selected to render engineering procurement construction services for the gas fired power project.
Siemens Energy was selected as the turbine supplier for the Gas fired project. The company provided 1 steam turbine with 75MW nameplate capacity.
Siemens Energy was selected as the turbine supplier for the Gas fired project. The company provided 3 units of SGT-1000 gas turbines, each with 65MW nameplate capacity.
Siemens Energy supplied electric generator for the project.
Siemens Energy supplied electric generator for the project.
Deutsche Babcock supplied steam boiler for the project.
Deutsche Babcock supplied steam boiler for the project.
For more details on Nossener Brucke Cogeneration Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.