Hondouji is a 75MW hydro power project. It is located on Sagaegawa river/basin in Yamagata, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1972 and subsequently entered into commercial operation in 1990. Buy the profile here.
Description
The project is currently owned by Tohoku Electric Power with a stake of 100%.
The hydro reservoir capacity is 109 million cubic meter. The net head of the project is 137.2m. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 1 in number. The penstock diameter is 3.2m.
Development status
The project construction commenced in 1972 and subsequently entered into commercial operation in 1990.
Contractors involved
Fuji Electric was selected as the turbine supplier for the hydro power project. The company provided 1 unit of francis turbine with 77MW nameplate capacity.
Fuji Electric supplied 1 electric generator for the project. The generator capacity is 83.4 MVA.
For more details on Hondouji, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.