Krasnodarskaya Combined Cycle Power Plant is a 440MW gas fired power project. It is located in Krasnodar Krai, Russia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in October 2011. Buy the profile here.
Description
The project is currently owned by Lukoil-Kubanenergo with a stake of 100%.
It is a CCGT with Cogen power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel.
Development status
The project got commissioned in October 2011.
Contractors involved
E4 Group was selected to render engineering procurement construction services for the gas fired power project.
The Gas fired project have been supplied by Mitsubishi Power and Ural Turbine Works.
The electric generators for the project were procured from Mitsubishi Power and NPO Elsib.
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the project.
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the project.
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the project.
Taganrog Boiler-Making Works Krasny Kotelshchik supplied steam boiler for the project.
For more details on Krasnodarskaya Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.