Belver is an 80.7MW hydro power project. It is located on Taju river/basin in Portalegre, Portugal. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1945 and subsequently entered into commercial operation in 1952. Buy the profile here.
Description
The project is currently owned by Energias de Portugal with a stake of 100%.
Belver is a run-of-river project. The hydro reservoir capacity is 7.5 million cubic meter. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 6 in number. The project generated 180 GWh of electricity.
Development status
The project construction commenced in 1945 and subsequently entered into commercial operation in 1952.
Contractors involved
GE Renewable Energy was selected as the turbine supplier for the hydro power project. The company provided 6 units of kaplan turbines, each with 13.45MW nameplate capacity.
GE Renewable Energy supplied electric generator(s) for the project.
For more details on Belver, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.