Tufanbeyli Coal Fired Power Plant is a 450MW coal fired power project. It is located in Adana, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in March 2016. Buy the profile here.
Description
The project is co-owned by E.ON and Haci Omer Sabanci Holding, with their respective ownership stake of 50% each.
It is a Steam Turbine power plant.
The project generated 2,631,000MWh of electricity.
Development status
The project got commissioned in March 2016.
Contractors involved
Itochu and SK Ecoplant were selected to render engineering procurement construction services for the coal fired power project.
Doosan Skoda Power was selected as the turbine supplier for the Coal fired project. The company provided 3 steam turbines, each with 150MW nameplate capacity.
Korea Electric Power Industrial Development is the O&M contractor for thermal power project.
For more details on Tufanbeyli Coal Fired Power Plant, buy the profile here.