Jeeralang Power Plant is a 466MW gas fired power project. It is located in Victoria, Australia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1979. Buy the profile here.
Description
The project is currently owned by EnergyAustralia with a stake of 100%.
It is a Gas Turbine power plant that is used for Peakload. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Distillate Fuel Oil. The fuel is procured from Bass Strait Pipeline.
The project emitted 178t of carbon dioxide emissions (CO2) a year.
Development status
The project got commissioned in 1979.
Power purchase agreement
The power generated from the project is sold to EnergyAustralia under a power purchase agreement.
Contractors involved
Jeeralang Power Plant (Jeeralang Power Plant A) is equipped with Siemens Energy V93.1 gas turbines. The phase consists of 4 gas turbines with 56.5MW nameplate capacity.
Jeeralang Power Plant (Jeeralang Power Plant B) is equipped with GE Vernova MS9001 gas turbines. The phase consists of 3 gas turbines with 80MW nameplate capacity.
Siemens Energy supplied electric generator for the Jeeralang Power Plant (Jeeralang Power Plant A).
GE Vernova supplied electric generator for the Jeeralang Power Plant (Jeeralang Power Plant B).
For more details on Jeeralang Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.