Huanza is a 90.6MW hydro power project. It is located on Pallca river/basin in Lima, Peru. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2010 and subsequently entered into commercial operation in 2014. Buy the profile here.
Description
The project is developed and owned by Empresa de Generacion Huanza.
Huanza is a run-of-river project. The gross head of the project is 654m. The penstock length is 2,800m. The project generated 482.017 GWh of electricity.
Development status
The project construction commenced in 2010 and subsequently entered into commercial operation in 2014.
Contractors involved
Astaris was selected to render engineering procurement construction services for the hydro power project.
Chongqing Water Turbine Works was selected as the turbine supplier for the hydro power project. The company provided 2 units of pelton turbines, each with 47.8MW nameplate capacity.
Chongqing Water Turbine Works supplied 2 electric generators for the project. The generator capacity is 53.2 MVA.
For more details on Huanza, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.