Pavlodar CHP-3 Plant is a 555MW coal fired power project. It is located in Pavlodar, Kazakhstan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1972. Buy the profile here.
Description
The project is currently owned by Pavlodar Energo Joint Stock with a stake of 100%.
It is a Steam Turbine with Cogen power plant. The fuel is procured from Ekibastuz Coal.
Development status
The project got commissioned in 1972.
Contractors involved
Ural Turbine Works was selected as the turbine supplier for the Coal fired project. The company provided 2 units of PT-65 / 75-130-13 steam turbines.
Ural Turbine Works was selected as the turbine supplier for the Coal fired project. The company provided 3 units of T-120 / 130-130PR2 steam turbines.
NPO Elsib supplied TVF-60-2, TVF-120-2, Hydrogen Cooled electric generator for the project.
NPO Elsib supplied TVF-60-2, TVF-120-2, Hydrogen Cooled electric generator for the project.
For more details on Pavlodar CHP-3 Plant, buy the profile here.