Hintermuhr is a 104MW hydro power project. It is located on schmalzgraben river/basin in Salzburg, Austria. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1988 and subsequently entered into commercial operation in 1991. Buy the profile here.
Description
The project is currently owned by Salzburg.
Hintermuhr is a pumped storage project. The gross head of the project is 601.35m. The project generated 180 GWh of electricity.
The hydro power project consists of 1 turbine with 36MW nameplate capacity.
Development status
The project construction commenced in 1988 and subsequently entered into commercial operation in 1991.
Contractors involved
Andritz Hydro was selected as the turbine supplier for the hydro power project. The company provided 1 unit of pump turbine with 68MW nameplate capacity.
Andritz Hydro supplied electric generator(s) for the project. The generator capacity is 78 MVA.
For more details on Hintermuhr, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.