Guodian Dawukou Power Plant Phase II is a 660MW coal fired power project. It is located in Ningxia, China. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 2010. Buy the profile here.
Description
The project is currently owned by China Energy Investment.
It is a Steam Turbine with Cogen power plant.
Development status
The project got commissioned in 2010.
Contractors involved
Shanghai Turbine was selected as the turbine supplier for thermal power project. The project consists of 2 units of CJK330-16.67/0.4538/538 turbines, each with 330MW nameplate capacity.
Shanghai Electric Group supplied QFSN 330-2 electric generator for the Guodian Dawukou Power Plant Phase II (Guodian Dawukou Power Plant Phase II Unit I).
Shanghai Electric Group supplied QFSN 330-2 electric generator for the Guodian Dawukou Power Plant Phase II (Guodian Dawukou Power Plant Phase II Unit II).
Shanghai Boiler Works supplied steam boiler for the Guodian Dawukou Power Plant Phase II (Guodian Dawukou Power Plant Phase II Unit I).
Shanghai Boiler Works supplied steam boiler for the Guodian Dawukou Power Plant Phase II (Guodian Dawukou Power Plant Phase II Unit II).
For more details on Guodian Dawukou Power Plant Phase II, buy the profile here.