Tuggen is an 118MW hydro power project. It is located on Ume river/basin in Vasterbotten, Sweden. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1957 and subsequently entered into commercial operation in 1961. Buy the profile here.
Description
Vattenfall and Holmen Energi are currently owning the project having ownership stake of 93.2% and 6.8% respectively.
Tuggen is a reservoir based project. The hydro reservoir capacity is 10.8 million cubic meter. Tuggen underwent through rehabilitation & modernization during 2020-2021. The project generated 441 GWh of electricity.
The hydro power project consists of 1 turbine.
Development status
The project construction commenced in 1957 and subsequently entered into commercial operation in 1961.
Contractors involved
GE Renewable Energy supplied 1 electric generator for the project. The generator capacity is 55 MVA.
GE Renewable Energy supplied 1 electric generator for the project. The generator capacity is 70 MVA.
For more details on Tuggen, buy the profile here.