Moncalieri Combined Cycle Power Plant is an 809MW gas fired power project. It is located in Piedmont, Italy. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in May 2005.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 809 | 809 | – | Active | Piedmont, Italy |
---|
Description
The project is currently owned by Iren Energia.
It is a CCGT with Cogen power plant.
Development Status
The project got commissioned in May 2005.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataContractors Involved
Ansaldo Energia was selected to render EPC services for the Moncalieri Combined Cycle Power Plant (Moncalieri Combined Cycle Power Plant Block II).
Moncalieri Combined Cycle Power Plant (Moncalieri Combined Cycle Power Plant Block I) is equipped with Siemens steam turbine. The phase consists of 1 steam turbine with 141MW nameplate capacity.
Moncalieri Combined Cycle Power Plant (Moncalieri Combined Cycle Power Plant Block I) is equipped with Siemens SGT5-4000F gas turbine. The phase consists of 1 gas turbine with 270MW nameplate capacity.
Moncalieri Combined Cycle Power Plant (Moncalieri Combined Cycle Power Plant Block II) is equipped with Ansaldo Energia steam turbine. The phase consists of 1 steam turbine with 138MW nameplate capacity.
Moncalieri Combined Cycle Power Plant (Moncalieri Combined Cycle Power Plant Block II) is equipped with Ansaldo Energia AE94.3A gas turbine. The phase consists of 1 gas turbine with 260MW nameplate capacity.
Siemens supplied TLRI 115/52, Air-Cooled electric generator for the Moncalieri Combined Cycle Power Plant (Moncalieri Combined Cycle Power Plant Block I).
Siemens supplied TLRI 100/36, Air-Cooled electric generator for the Moncalieri Combined Cycle Power Plant (Moncalieri Combined Cycle Power Plant Block I).
Ansaldo Energia supplied WX21Z-092RR, Air-Cooled electric generator for the Moncalieri Combined Cycle Power Plant (Moncalieri Combined Cycle Power Plant Block II).
Ansaldo Energia supplied WY23Z-109LL, Air-Cooled electric generator for the Moncalieri Combined Cycle Power Plant (Moncalieri Combined Cycle Power Plant Block II).
AC Boilers supplied steam boiler for the Moncalieri Combined Cycle Power Plant (Moncalieri Combined Cycle Power Plant Block I).
AC Boilers supplied steam boiler for the Moncalieri Combined Cycle Power Plant (Moncalieri Combined Cycle Power Plant Block II).
Ansaldo Energia is the O&M contractor for thermal power project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.