Sumrall II Solar PV Park is a 68MW solar PV power project. It is located in Mississippi, the US. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in June 2017.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Solar PV 68 68 Active Mississippi, the US Origis Energy

Description

The project was developed by Origis Energy. DE Shaw Renewable Investments and Mississippi Power are currently owning the project.

Sumrall II Solar PV Park is a ground-mounted solar project which is spread over an area of 600 acres.

The project generates 130GWh electricity and supplies enough clean energy to power 8,000 households, offsetting 54,672t of carbon dioxide emissions (CO2) a year. The project cost is $100m.

Development Status

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

The project got commissioned in June 2017.

Power Purchase Agreement

The power generated from the project is sold to Mississippi Power under a power purchase agreement for a period of 25 years.

Contractors Involved

DEPCOM Power was selected to render EPC services for the solar PV power project.

Hanwha Q Cells was selected as the supplier of the PV modules for the project. The company installed 220,000 modules at the site.

The project is utilising single axis trackers supplied by NEXTracker.

DEPCOM Power is the O&M contractor for the solar PV power project.

About Origis Energy

Origis Energy (Origis) is a Belgium based fund and asset management group. It is principally engaged in creation, syndication and management of renewable energy related assets and cash flow based investments. The key services of the company include, site development, financing, engineering, procurement, construction and management. Origis is headquartered in Waregem, Belgium.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.