Pesqueria Combined Cycle Power Plant is a 900MW gas fired power project. It is located in Nuevo Leon, Mexico. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in March 2017.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 900 | 900 | – | Active | Nuevo Leon, Mexico | Techgen S.A. de |
---|
Description
The project is developed and owned by Techgen S.A. de. The company has a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The fuel is procured from Kinder-Morgan Transportation.
The project generated 6,387,000MWh of electricity. The project cost is $1,100m.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project got commissioned in March 2017.
Power Purchase Agreement
The power generated from the project is sold to Comision Federal de Electricidad under a power purchase agreement.
Contractors Involved
Techint E&C was selected to render EPC services for the gas fired power project.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 3 units of 7FA.05 gas turbines.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of D11 steam turbine.
GE Power supplied electric generator for the project.
GE Power is the O&M contractor for thermal power project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.