Tacoma Cogen Power Plant is a 60MW biopower project. It is located in Washington, the US. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in August 2009.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Biopower | 60 | 60 | – | Active | Washington, the US |
---|
Description
The project generates 27.5GWh electricity and supplies enough clean energy to power 38,000 households, offsetting 300,000t of carbon dioxide emissions (CO2) a year. The project cost is $90m.
The process of combustion has been adopted in this combined heat and power (CHP) project to release the stored energy from the feed. Industrial waste, municipal solid waste and wood by-product are used as a feedstock to power the project.
Development Status
The project got commissioned in August 2009.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataPower Purchase Agreement
The power generated from the project is sold to Avangrid Renewables under a power purchase agreement for a period of 10 years. The contracted capacity is 60MW.
Contractors Involved
Siemens was selected as the steam turbine supplier for the project. The company supplied Triple Extraction Condensing Turbine model turbines for the project.
Riley Stoker supplied steam boiler for the project. The boiler installed at the site has a capacity of 154.22TPH. The steam is pressurized inside the boiler at 875psig.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.