Phu My 2-2 Combined Cycle Power Plant is a 729.4MW gas fired power project. It is located in Ba Ria-Vung Tau, Vietnam. The project is currently active. It has been developed in single phase. The project construction commenced in 2003 and subsequently entered into commercial operation in February 2005.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 729.4 | 729.4 | – | Active | Ba Ria-Vung Tau, Vietnam | Mekong Energy |
---|
Description
The project was developed by Mekong Energy. EDF Energy Holdings, Sumitomo and JERA are currently owning the project having ownership stake of 56.25%, 28.12% and 15.62% respectively.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel. The fuel is procured from Petro Vietnam from the Nam Con Son Basin.
The project cost is $480m.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project construction commenced in 2003 and subsequently entered into commercial operation in February 2005.
Power Purchase Agreement
The power generated from the project is sold to Vietnam Electricity under a power purchase agreement for a period of 20 years. The contracted capacity is 729.4MW.
Contractors Involved
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 2 units of 9F.03 gas turbines, each with 226.2MW nameplate capacity.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of D11-TC2F steam turbine with 277MW nameplate capacity.
GE Power supplied Hydrogen-Cooled electric generator for the project.
Siemens Heat Transfer Technology supplied steam boiler for the project.
Mekong Energy is the O&M contractor for thermal power project.
About Mekong Energy
MEKONG ENERGY COMPANY LTD. is an independent power producer. MEKONG ENERGY COMPANY LTD. is able to produce roughly 40 % of the maximum electricity demand in Vietnam.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.