The Trumbull Energy Center II is 950MW gas fired power project. It is planned in Ohio, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. The project construction is likely to commence in 2022 and is expected to enter into commercial operation in January 2026. Buy the profile here.
Description
The project is being developed and currently owned by Clean Energy Future Trumbull. The company has a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant that will be used for Peakload. The fuel will be procured from Dominion East Ohio pipeline.
Development status
The project construction is expected to commence from 2022. Subsequent to that it will enter into commercial operation by January 2026.
Contractors involved
Gemma Power Systems is expected to render engineering procurement construction services for the gas fired power project.
Siemens Energy will be the turbine supplier for the Gas fired project. The company is expected to provide2 gas turbines, each with 350MW nameplate capacity.
Siemens Energy will be the turbine supplier for the Gas fired project. The company is expected to provide1 steam turbine with 350MW nameplate capacity.
Siemens Energy is expected to be the supplier of Sgen6-2000H electric generator for the project.
Siemens Energy is likely to be the supplier of steam boiler for the project.
For more details on Trumbull Energy Center II, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.