Kerman Combined Cycle Power Plant is a 1,912MW gas fired power project. It is located in Kerman, Iran. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in March 2007. Buy the profile here.
Description
The project is currently owned by Iran Power Development.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Diesel. The fuel is procured from Sarkhoun Refinery.
Development status
The project got commissioned in March 2007.
Contractors involved
MAPNA Combined Cycle Power plants Constraction & Development was selected to render engineering procurement construction services for the gas fired power project.
Kerman Combined Cycle Power Plant (Kerman Combined Cycle Power Plant Block I) is equipped with Ansaldo Energia V94.2 gas turbines. The phase consists of 2 gas turbines with 159MW nameplate capacity.
Kerman Combined Cycle Power Plant (Kerman Combined Cycle Power Plant Block I) is equipped with MAPNA Turbine Engineering & Manufacturing E-Type steam turbine. The phase consists of 1 steam turbine with 160MW nameplate capacity.
Kerman Combined Cycle Power Plant (Kerman Combined Cycle Power Plant Block II) is equipped with Ansaldo Energia V94.2 gas turbines. The phase consists of 2 gas turbines with 159MW nameplate capacity.
Kerman Combined Cycle Power Plant (Kerman Combined Cycle Power Plant Block II) is equipped with MAPNA Turbine Engineering & Manufacturing E-Type steam turbine. The phase consists of 1 steam turbine with 160MW nameplate capacity.
Kerman Combined Cycle Power Plant (Kerman Combined Cycle Power Plant Block III) is equipped with Ansaldo Energia V94.2 gas turbines. The phase consists of 2 gas turbines with 159MW nameplate capacity.
Kerman Combined Cycle Power Plant (Kerman Combined Cycle Power Plant Block III) is equipped with MAPNA Turbine Engineering & Manufacturing E-Type steam turbine. The phase consists of 1 steam turbine with 160MW nameplate capacity.
Kerman Combined Cycle Power Plant (Kerman Combined Cycle Power Plant Block IV) is equipped with Ansaldo Energia V94.2 gas turbines. The phase consists of 2 gas turbines with 159MW nameplate capacity.
Kerman Combined Cycle Power Plant (Kerman Combined Cycle Power Plant Block IV) is equipped with MAPNA Turbine Engineering & Manufacturing E-Type steam turbine. The phase consists of 1 steam turbine with 160MW nameplate capacity.
MAPNA Generator Engineering & Manufacturing supplied electric generator for the project.
MAPNA Generator Engineering & Manufacturing supplied electric generator for the project.
GE Power supplied steam boiler for the project.
GE Power supplied steam boiler for the project.
For more details on Kerman Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.