Svartisen is a 600MW hydro power project. It is located on Svartisen glacier river/basin in Nordland, Norway. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1993. Buy the profile here.
Description
Statkraft and Nordland County Council are currently owning the project having ownership stake of 70% and 30% respectively.
Svartisen is a reservoir based project. The hydro reservoir capacity is 3,500 million cubic meter. The gross head of the project is 585m. The project generated 2,195.5 GWh of electricity.
Development status
The project got commissioned in 1993.
Contractors involved
Rainpower was selected as the turbine supplier for the hydro power project. The company provided 1 unit of francis turbine with 250MW nameplate capacity.
Rainpower was selected as the turbine supplier for the hydro power project. The company provided 1 unit of francis turbine with 350MW nameplate capacity.
The electric generators for the project were procured from GE Renewable Energy and Voith Hydro Holding.
For more details on Svartisen, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.