Cilacap Steam Turbine Power Plant is a 2,260MW coal fired power project. It is located in Central Java, Indonesia. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in April 2006. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Cilacap Steam Turbine Power Plant

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project was developed by PT Sumber Segara Primadaya. PT Sumberenergi Sakti Prima and PT PLN Nusantara Power are currently owning the project having ownership stake of 51% and 49% respectively.

It is a Steam Turbine power plant.

Cilacap Steam Turbine Power Plant (Cilacap Steam Turbine Power Plant Expansion) consists of 1 steam turbine with 1,000MW nameplate capacity.

Cilacap Steam Turbine Power Plant (Cilacap Steam Turbine Power Plant Unit I) consists of 1 steam turbine with 300MW nameplate capacity.

Cilacap Steam Turbine Power Plant (Cilacap Steam Turbine Power Plant Unit II) consists of 1 steam turbine with 300MW nameplate capacity.

Development status

The project got commissioned in April 2006.

Power purchase agreement

The power generated from the project is sold to PT PLN (Persero) under a power purchase agreement.

Contractors involved

China Chengda Engineering was selected to render engineering procurement construction services for the coal fired power project.

Cilacap Steam Turbine Power Plant (Cilacap Steam Turbine Power Plant Unit III) is equipped with Shanghai Electric Group steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.

Babcock & Wilcox Beijing supplied steam boiler for the Cilacap Steam Turbine Power Plant (Cilacap Steam Turbine Power Plant Unit III).

Babcock & Wilcox Beijing supplied steam boiler for the Cilacap Steam Turbine Power Plant (Cilacap Steam Turbine Power Plant Unit III).

PT Pembangkitan Jawa Bali Services is the O&M contractor for the Cilacap Steam Turbine Power Plant (Cilacap Steam Turbine Power Plant Unit I).

PT Pembangkitan Jawa Bali Services is the O&M contractor for the Cilacap Steam Turbine Power Plant (Cilacap Steam Turbine Power Plant Unit II).

For more details on Cilacap Steam Turbine Power Plant, buy the profile here.

About PT Sumber Segara Primadaya

PT Sumber Segara Primadaya (S2P) is a power producer company. It generates and transmits electricity and operates power plants. It produces electricity using coal sources. S2P operates the coal fired Cilacap power station with units 1, 2 and 3 that utilize supercritical boiler and flue gas desulfurization technology for power production in Central Java Province. The company is a joint venture of PT Sumberenergi Sakti Prima and PT Pembangkit Jawa Bali. The company operates across Indonesia. S2P is headquartered in Jakarta, Indonesia.

This content was updated on 14 October 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.