Chhabra Thermal Power Station is a 2,320MW coal fired power project. It is located in Rajasthan, India. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in June 2010.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 2,320 | 2,320 | – | Active | Rajasthan, India | Rajasthan Rajya Vidyut Prasaran Nigam |
---|
Description
The project was developed by Rajasthan Rajya Vidyut Prasaran Nigam and is currently owned by Rajasthan Rajya Vidyut Utpadan Nigam.
It is a steam turbine power plant. The fuel is procured from South Eastern Coalfields Limited-Korba, Parsa & Kante Colleries Ltd.-Ambikapur.
The project generated 3,158,449MWh of electricity. The project cost is $2,187.4m.
Development Status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe project got commissioned in June 2010.
Power Purchase Agreement
Ajmer Vidyut Vitran Nigam, Jaipur Vidyut Vitran Nigam and Jodhpur Vidyut Vitran Nigam are the power offtakers from the project.
Contractors Involved
L&T-Sargent & Lundy was selected to render EPC services for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage – II Extension Unit I) project. L&T-Sargent & Lundy was selected to render EPC services for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage – II Extension Unit II) project.
Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage – II Extension Unit I) is equipped with L&T-MHI Power Turbine Generators steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.
Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage – II Extension Unit II) is equipped with L&T-MHI Power Turbine Generators steam turbine. The phase consists of 1 steam turbine with 660MW nameplate capacity.
Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage I Unit I) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage I Unit II) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage II Unit I) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage II Unit II) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 250MW nameplate capacity.
L&T-MHI Power Turbine Generators supplied electric generator for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage – II Extension Unit I).
L&T-MHI Power Turbine Generators supplied electric generator for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage – II Extension Unit II).
Bharat Heavy Electricals supplied electric generator for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage I Unit I).
Bharat Heavy Electricals supplied electric generator for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage I Unit II).
Bharat Heavy Electricals supplied electric generator for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage II Unit I).
Bharat Heavy Electricals supplied electric generator for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage II Unit II).
L&T-MHPS Boilers supplied steam boiler for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage – II Extension Unit I).
L&T-MHPS Boilers supplied steam boiler for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage – II Extension Unit II).
Bharat Heavy Electricals supplied steam boiler for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage I Unit I).
Bharat Heavy Electricals supplied steam boiler for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage I Unit II).
Bharat Heavy Electricals supplied steam boiler for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage II Unit I).
Bharat Heavy Electricals supplied steam boiler for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage II Unit II).
Sterling and Wilson is the O&M contractor for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage – II Extension Unit I).
Sterling and Wilson is the O&M contractor for the Chhabra Thermal Power Station (Chhabra Thermal Power Station Stage – II Extension Unit II).
About Rajasthan Rajya Vidyut Prasaran Nigam
Rajasthan Rajya Vidyut Prasaran Nigam Ltd (RRVPN) is a power company which provide services through generation, trasmission and distribution of electricity. RRVPN is headquartered in India.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.