Kainji is a 760MW hydro power project. It is located on Niger river/basin in Niger, Nigeria. The project is currently active. It has been developed in multiple phases. The project construction commenced in 1964 and subsequently entered into commercial operation in 1968.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 760 760 Active Niger, Nigeria Mainstream Energy Solutions

Description

The project is developed and owned by Mainstream Energy Solutions.

The hydro reservoir capacity is 15,000 million cubic meter. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 12 in number. The penstock diameter is 8.55m.

Development Status

The project construction commenced in 1964 and subsequently entered into commercial operation in 1968.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Contractors Involved

Kainji (Phase-1-Kainji Unit no. 9,10) is equipped with The English Electric kaplan turbines. The phase consists of 2 turbines with 80MW nameplate capacity.

Kainji (Phase-2-Kainji Unit no. 12) is equipped with Andritz Hydro kaplan turbine. The phase consists of 1 turbine with 100MW nameplate capacity.

Kainji (Phase-3-Kainji Unit no. 3,5,6) is equipped with Andritz Hydro propeller turbines. The phase consists of 2 turbines with 120MW nameplate capacity.

Kainji (Phase-4-Kainji Unit no. 11) is equipped with Andritz Hydro kaplan turbine. The phase consists of 1 turbine with 100MW nameplate capacity.

Kainji (Phase-5-Kainji Unit no. 7,8) is equipped with GE Renewable Energy kaplan turbines. The phase consists of 2 turbines with 80MW nameplate capacity.

GE Renewable Energy supplied 2 electric generators for the Kainji (Phase-1-Kainji Unit no. 9,10). The generator capacity is 85 MVA.

GE Renewable Energy supplied 2 electric generators for the Kainji (Phase-5-Kainji Unit no. 7,8). The generator capacity is 85 MVA.

About Mainstream Energy Solutions

Mainstream Energy Solutions Ltd. (Mainstream Energy Solutions) is a hydroelectric power generation plant. The Company generates electricity and sells it to distributors. It is headquartered in Abuja, Nigeria.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.