Ramagundam Super Thermal Power Station is a 2,600MW coal fired power project. It is located in Telangana, India. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in March 1984. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Ramagundam Super Thermal Power Station

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by NTPC with a stake of 100%.

It is a Steam Turbine power plant that is used for Baseload. The power plant run on dual-fuel. The primary fuel being used to power the plant is coal. In case of shortage of coal the plant can also run on Heavy Fuel Oil. The fuel is procured from South Godavari Coal Fields of Singrani Collieries, Korba Coal Fields of SECL.

The project generated 20,443,000MWh of electricity.

Development status

The project got commissioned in March 1984.

Contractors involved

Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage I Unit I) is equipped with Ansaldo Energia steam turbine. The phase consists of 1 steam turbine with 200MW nameplate capacity.

Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage I Unit II) is equipped with Ansaldo Energia steam turbine. The phase consists of 1 steam turbine with 200MW nameplate capacity.

Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage I Unit III) is equipped with Ansaldo Energia steam turbine. The phase consists of 1 steam turbine with 200MW nameplate capacity.

Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage II Unit I) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 500MW nameplate capacity.

Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage II Unit II) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 500MW nameplate capacity.

Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage II Unit III) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 500MW nameplate capacity.

Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage III) is equipped with Bharat Heavy Electricals steam turbine. The phase consists of 1 steam turbine with 500MW nameplate capacity.

Ansaldo Energia supplied electric generator for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage I Unit I).

Ansaldo Energia supplied electric generator for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage I Unit II).

Ansaldo Energia supplied electric generator for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage I Unit III).

Bharat Heavy Electricals supplied electric generator for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage II Unit I).

Bharat Heavy Electricals supplied electric generator for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage II Unit II).

Bharat Heavy Electricals supplied electric generator for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage II Unit III).

Bharat Heavy Electricals supplied electric generator for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage III).

AC Boilers supplied steam boiler for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage I Unit I).

AC Boilers supplied steam boiler for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage I Unit II).

AC Boilers supplied steam boiler for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage I Unit III).

Bharat Heavy Electricals supplied steam boiler for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage II Unit I).

Bharat Heavy Electricals supplied steam boiler for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage II Unit II).

Bharat Heavy Electricals supplied steam boiler for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage II Unit III).

Bharat Heavy Electricals supplied steam boiler for the Ramagundam Super Thermal Power Station (Ramagundam Super Thermal Power Station Stage III).

NTPC is the O&M contractor for thermal power project.

For more details on Ramagundam Super Thermal Power Station, buy the profile here.

This content was updated on 14 October 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.