Matiari – Lahore HVDC Line is a 660kV overhead line with a length of 878km from Matiari, Sindh, Pakistan, to Lahore, Punjab, Pakistan.
The project, which is currently under construction, is expected to be commissioned in 2021.
Description
Matiari – Lahore HVDC Line is an overhead line that will be operated by National Transmission & Despatch. The line will carry direct current (AC) through double circuit cable.
The development of the Matiari – Lahore HVDC Line project has been approved by the Water and Power Development Authority,Pakistan.
Matiari – Lahore HVDC Line project development status
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataThe construction works on the Matiari – Lahore HVDC Line project were commenced in 2018 and commissioning is expected in 2021.
About National Transmission & Despatch
National Transmission & Despatch Co Ltd (NTDC) operates as an electric utility that generates, transmits, dispatch and distributes electricity. The company operates and maintains a network of grid stations and transmission lines. Its services offerings include planning and design, operations and maintenance, monitoring and testing, pre-commissioning test, technical analysis, technical auditing, thermovision survey and technical training services. NTDC also provides online bill payment, rebates and incentives, electrical safety, energy conservation, outage reporting, load management, energy assistance and meter reading services.
Methodology
All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.