Samnanger Substation is a 400kV substation located in Samnanger, Hordaland, Norway.

The Samnanger Substation project’s construction has begun in 2021. The works are expected to be commissioned in 2022.

Description

Samnanger Substation project, which is an upgrade substation, will be operated by Statnett SF.

The designed voltage level of the substation is 400/132kV and the operating voltage level is 400/132kV.

The step-in voltage of the project is 400kV and the step-out voltage is 132kV. Upon completion, the substation will have a capacity of 300MVA.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Samnanger Substation project development status

The development of the Samnanger Substation project was approved by Norwegian Water Resources and Energy Directorate in 2021. The project is expected to be commissioned in 2022.

About Statnett SF

Statnett SF (Statnett) is an energy utility company that transmits and distributes electricity through its grid infrastructure. The company operates, develop, maintain and monitor transmission grid, cables and power lines of the Norwegian energy system. It has a communication network of optical fibre to monitor and control from its one national control center and three regional centers in Norway facilities. The company has a presence in Sweden, Finland, Russia, Denmark and the Netherlands. Statnett serves residential, industrial and commercial consumers in Norway. Statnett is headquartered in Raipas, Norway.

Methodology

All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.