Borssele – Tilburg Line is a 380kV overhead line from Borssele, Zeeland, Netherlands, to Tilburg, North Brabant, Netherlands.

Construction works on the Borssele – Tilburg Line project was commissioned in 2016.

Description

The Borssele – Tilburg Line, which is an overhead line, is being operated by TenneT TSO. The Borssele – Tilburg Line is a new line. The line carries alternating current (AC) through double circuit cable.

Borssele – Tilburg Line project development status

The development of the Borssele – Tilburg Line project was approved by The Netherlands Authority for Consumers and Markets and the project works were completed in 2016.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

About TenneT TSO

TenneT TSO B.V. (TenneT TSO), a subsidiary of TenneT Holding BV, is an electricity transmission system operator. The company operates and maintains electric power transmission grids for transmitting the high voltage energy. Along with electricity transmission it also provides gas transmission across borders. TenneT TSO also offers grid maintenance services. Its operations are spread across the Netherlands and Germany. TenneT TSO is headquartered in Arnhem, Gelderland, the Netherlands.

Methodology

All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.