Blackwater Draw – Double Mountain Line is a 345kV overhead line with a length of 53.1km from Blackwater Draw, Texas, US, to Double Mountain, Stonewall County, Texas, US.
The project, which is currently in the planning stage, is expected to be commissioned in 2022.
Description
Blackwater Draw – Double Mountain Line is an overhead line that will be operated by Oncor Electric Delivery. The line will carry alternating current (AC) through double circuit cable.
Blackwater Draw – Double Mountain Line project development status
The construction works on the Blackwater Draw – Double Mountain Line project will be commenced in 2021 and commissioning is expected in 2022.
How well do you really know your competitors?
Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.
Thank you!
Your download email will arrive shortly
Not ready to buy yet? Download a free sample
We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form
By GlobalDataAbout Oncor Electric Delivery
Oncor Electric Delivery Co LLC (Oncor) is a regulated electricity transmission and distribution company that operates distribution and transmission systems. It provides transmission grid connections to merchant generation facilities and interconnections to other transmission grids. The company also provides planning, design, construct, operate and maintain services for the transmission grids; and own the load-serving substations primarily within certified distribution service areas.
Methodology
All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.