Bannu Substation is a 500kV substation located in Bannu, Khyber Pakhtunkhwa, Pakistan.

The Bannu Substation project’s construction is expected to begin in 2023. The works are expected to be commissioned in 2024.

Description

Bannu Substation project, which is an upgrade substation, will be operated by National Transmission & Despatch.

The designed voltage level of the substation is 500/220kV and the operating voltage level is 500/220kV.

The step-in voltage of the project is 500kV and the step-out voltage is 220kV. Upon completion, the substation will have a capacity of 2250MVA.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Bannu Substation project development status

The project is expected to be commissioned in 2024.

About National Transmission & Despatch

National Transmission & Despatch Co Ltd (NTDC) operates as an electric utility that generates, transmits, dispatch and distributes electricity. The company operates and maintains a network of grid stations and transmission lines. Its services offerings include planning and design, operations and maintenance, monitoring and testing, pre-commissioning test, technical analysis, technical auditing, thermovision survey and technical training services. NTDC also provides online bill payment, rebates and incentives, electrical safety, energy conservation, outage reporting, load management, energy assistance and meter reading services.

Methodology

All publicly-announced T&D Line & Substation projects included in this analysis are drawn from GlobalData’s Power IC. The information regarding the projects is sourced through secondary information sources such as country specific utility players, company news and reports, statistical organisations, regulatory body, government planning reports and their publications and is further validated through primary from various stakeholders such as power utility companies, consultants, energy associations of respective countries, government bodies and professionals from leading players in the power sector.